Power plant · Rhondda Cynon Taf, Wales, United Kingdom
Coed Ely - Solar Farm
Coed Ely - Solar Farm is a power plant under construction in Rhondda Cynon Taf, Wales, United Kingdom, with 6 MW of capacity, operated by Rhondda Cynon Taff County Borough Council.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Rhondda Cynon Taf (coordinates), Wales | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Former Coedely Colliery, Off A4119, Tonyrefail, CF39 8PX | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Under construction | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 5 Dec 2023 (permit 23/0994/08, Town and Country Planning Act, issued by Rhondda Cynon Taf) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 11 Sept 2023 (reference 23/0994/08, planning authority Rhondda Cynon Taf) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 5 Dec 2023 (granted, reference 23/0994/08, planning authority Rhondda Cynon Taf) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Rhondda Cynon Taff County Borough Council | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 6 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 16.9 ha (solar site area) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 51.5676, -3.4161 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Construction started
- Permit granted (planning authority Rhondda Cynon Taf, reference 23/0994/08)
- Permit applied for (planning authority Rhondda Cynon Taf, reference 23/0994/08)
How it compares
Coed Ely - Solar Farm is the 130th-largest of 177 power plants planned, permitted or under construction in Wales and the 2,433rd-largest of 3,222 in the United Kingdom by capacity; its 6 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| Wales | 130th of 177 | 16,801 MW | <0.1% |
| United Kingdom | 2,433rd of 3,222 | 300,461 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 5,556th of 6,455 | 664,040 MW | <0.1% |
Nearby
Within 50 km of this power plant: 8 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 4, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| CGI Datacenter | Data center | — | — | 14 km |
| Centerprise International (Distribution) | Data center | — | — | 15 km |
| Microsoft Newport data centre | Data center | — | — | 26 km |
| Hinkley Point C Connection Project Material Change | Transmission line | — | Planned | 47 km |
Operator and place
Other power plants in Wales
- Dinorwig1,728 MW
- Gwynt y Mor576 MW
- Ffestiniog360 MW
- Port Talbot Renewable Energy Plant350 MW
- Anglesey Biomass Power Station299 MW
- Tidal Lagoon Swansea Bay240 MW
- Pen Y Cymoedd228 MW
- Carnedd Wen Wind Farm150 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.