Power plant · Aberdeenshire, Scotland, United Kingdom

Hillhead Of Gask, Longhaven - Solar Array

Hillhead Of Gask, Longhaven - Solar Array is a power plant under construction in Aberdeenshire, Scotland, United Kingdom, with 14.2 MW of capacity, operated by The Greenspan Agency.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationAberdeenshire (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressHillhead Of Gask Longhaven Peterhead, AB42 0PTDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusUnder constructionDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date8 Apr 2022 (permit APP/2021/2467, Town and Country Planning Act, issued by Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date14 Jan 2022 (ref. APP/2021/2467, Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date8 Apr 2022 (granted, ref. APP/2021/2467, Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorThe Greenspan AgencyDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity14.2 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area19.1 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates57.4646, -1.8525DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Hillhead Of Gask, Longhaven - Solar Array is the 659th-largest of 872 power plants planned, permitted or under construction in Scotland and the 2,152nd-largest of 3,222 in the United Kingdom by capacity; its 14.2 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland659th of 87299,272 MW<0.1%
United Kingdom2,152nd of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data4,589th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 103 grid connections (45 operating, 262 MW) and 64 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Wells Forest Farm 25MW grid connectionGrid connection50.2 MWPlanned0.9 km
Stoneyhill Landfill grid connectionGrid connection1.94 MWOperating0.9 km
Hillhead of Gask PV and BESS grid connectionGrid connection14.2 MWPlanned0.9 km
Stoneyhill PrimarySubstation——1.3 km
Peterhead Shell GSPSubstation——3.3 km
Boddam PrimarySubstation——3.4 km

Operator and place

Grid connections attached to this power plant

More from The Greenspan Agency

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom