Power plant · Bassetlaw, England, United Kingdom
Walmoor Farm solar park
Walmoor Farm solar park is a power plant in Bassetlaw, England, United Kingdom, with 4 MW of capacity, operated by Green Switch Solutions.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Bassetlaw (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Land To South West Of Greenfields Grove Road Retford Nottinghamshire, DN22 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 2015 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 22 Apr 2014 (permit 14/00034/FUL, Town and Country Planning Act, issued by Bassetlaw) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 21 Jan 2014 (reference 14/00034/FUL, planning authority Bassetlaw) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 22 Apr 2014 (granted, reference 14/00034/FUL, planning authority Bassetlaw) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Green Switch Solutions | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 4 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 53.3034, -0.9163 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
How it compares
Walmoor Farm solar park is the 2,350th-largest of 3,430 power plants in England and the 3,494th-largest of 5,050 in the United Kingdom by capacity; its 4 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 2,350th of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 3,494th of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 9,252nd of 12,008 | 1,173,302 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Permit issued (Town and Country Planning Act), no. 14/00034/FUL
- Started operating
Nearby
Within 50 km of this power plant: 434 grid connections (112 operating, 1,395 MW), 155 substations, 7 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Walmoor Farm Retford grid connection | Grid connection | — | — | 0.2 km |
| Brecks Farm grid connection | Grid connection | — | — | 3.2 km |
| Land OFF, Brecks Farm grid connection | Grid connection | — | — | 3.2 km |
| Lea Road | Substation | — | — | 14 km |
| Stow | Substation | — | — | 15 km |
| Corringham Road | Substation | — | — | 15 km |
| North Humber to High Marnham | Transmission line | — | Planned | 18 km |
| Thales | Data center | — | — | 26 km |
| Digital Space DC - Newark | Data center | — | — | 26 km |
Operator and place
More from Green Switch Solutions
- Partridge Hill Solar Farm33 MW · permitted
- Wanes Blades Road Solar Farm16 MW
- Clay Tye Farm15.9 MW
- Wharrels Hill14.6 MW
- Hurst Hall13.3 MW
- Grange Farm (Lincolnshire)12.7 MW
- Land at Rectory Farm8.9 MW
- GDL Wymeswold Solar Farm/land off the A60066.1 MW
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- NGED Connected Data portal. NGED Connected Data portal, Terms not verified.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.