The Brickmakers Arms Battery is a cancelled battery storage plant in Bedford, England, United Kingdom, with 20 MW of capacity, operated by FPC Industry & Enterprise 2 Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationBedford (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressThe Brickmakers Arms Ph Woburn Road, Kempston Hardwick Bedford, MK43 9AHDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission granted, permission expired)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date22 Dec 2021 (permit 21/00300/FUL, Town and Country Planning Act, issued by Bedford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date2 Feb 2021 (reference 21/00300/FUL, planning authority Bedford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date22 Dec 2021 (granted, reference 21/00300/FUL, planning authority Bedford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorFPC Industry & Enterprise 2 Limited (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity20 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.0971, -0.5076DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Bedford, reference 21/00300/FUL)
  2. Permit applied for (planning authority Bedford, reference 21/00300/FUL)

How it compares

The Brickmakers Arms Battery is the 877th-largest of 4,035 power plants in England and the 1,479th-largest of 5,834 in the United Kingdom by capacity; its 20 MW is <0.1% of the 200,500 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England877th of 4,035134,434 MW<0.1%
United Kingdom1,479th of 5,834200,500 MW<0.1%
All power plants in our data6,712th of 15,7991,918,113 MW<0.1%

Nearby

Within 50 km of this power plant: 16 data centers, 9 grid connections (3 operating, 23.9 MW) and 8 substations, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Pulsant Milton Keynes SE-1Data center——18 km
Data center, England (OSM way 460010263)Data center——18 km
nLighten Milton KeynesData center——22 km
East Claydon GSPSubstation——33 km
Pembridge Farm grid connectionGrid connection131 MWPlanned42 km
Shelswell Solar Park grid connectionGrid connection4.75 MWOperating44 km
Bicester 49.9MW - PV grid connectionGrid connection44 MWPlanned44 km
Cottisford PrimarySubstation——45 km
Bicester North BSPSubstation——48 km