Power plant · Darlington, England, United Kingdom
Rise Carr, Darlington / CLNR EES3-1
Rise Carr, Darlington / CLNR EES3-1 is a power plant in Darlington, England, United Kingdom, with 2.5 MW of capacity, operated by Northern Powergrid.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Darlington (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Rise Carr, Darlington, DL3 0RX | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 2014 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Northern Powergrid | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 2.5 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Battery | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 54.5473, -1.5560 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
How it compares
Rise Carr, Darlington / CLNR EES3-1 is the 2,673rd-largest of 3,430 power plants in England and the 3,943rd-largest of 5,050 in the United Kingdom by capacity; its 2.5 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 2,673rd of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 3,943rd of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 9,997th of 12,008 | 1,173,302 MW | <0.1% |
Nearby
Within 50 km of this power plant: 257 grid connections (130 operating, 1,291 MW) and 142 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Rise Carr | Substation | — | — | 0.2 km |
| Darlington North | Substation | — | — | 1.0 km |
| Gas 2.5 MW grid connection at Darlington West | Grid connection | 2.5 MW | Operating | 1.7 km |
| Darlington 132/6kV Direct | Substation | — | — | 2.3 km |
| Solar 40 MW grid connection at Whessoe PV | Grid connection | 40 MW | Planned | 2.4 km |
| Battery storage and Solar 61.9 MW grid connection at Stanley Farm Hybrid | Grid connection | 61.9 MW | Planned | 2.8 km |
Operator and place
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.