Power plant · Stockton-on-Tees, England, United Kingdom

Port Clarence Biomass Plant

Port Clarence Biomass Plant is a power plant under construction in Stockton-on-Tees, England, United Kingdom, with 40 MW of capacity, operated by Glennmont Partners.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationStockton-on-Tees (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressPort Clarence Road, Port Clarence,DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusUnder constructionDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date23 Feb 2010 (permit S/CON/0038/10/P, Town and Country Planning Act, issued by Stockton-on-Tees)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date14 Jan 2010 (ref. S/CON/0038/10/P, Stockton-on-Tees)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date23 Feb 2010 (granted, ref. S/CON/0038/10/P, Stockton-on-Tees)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorGlennmont PartnersDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity40 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBiomass (dedicated)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates54.5888, -1.2275DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Port Clarence Biomass Plant is the 836th-largest of 2,174 power plants planned, permitted or under construction in England and the 1,342nd-largest of 3,222 in the United Kingdom by capacity; its 40 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England836th of 2,174186,088 MW<0.1%
United Kingdom1,342nd of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data2,556th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 245 grid connections (126 operating, 1,265 MW) and 141 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Solar 1.26 MW grid connection at North Tees T3 T4Grid connection1.26 MWPlanned0.0 km
Waste 4.921 MW grid connection at Faraday StreetGrid connection4.92 MWOperating1.3 km
Gas 61.75 MW grid connection at Viking PowerGrid connection61.8 MWOperating1.4 km
SaltholmeSubstation——2.0 km
North TeesSubstation——2.1 km
North Tees T1 T2Substation——2.1 km

Operator and place