Power plant · South Staffordshire, England, United Kingdom

Pool Hall Farm, Lower Penn - Battery Storage

Pool Hall Farm, Lower Penn - Battery Storage is a permitted power plant in South Staffordshire, England, United Kingdom, with 100 MW of capacity, operated by Elgin Energy EsCo.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSouth Staffordshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressPool Hall Farm Lower Penn, WV4 4XNDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date21 Jul 2025 (permit 24/01092/FULM, Town and Country Planning Act, issued by South Staffordshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date7 Jan 2025 (reference 24/01092/FULM, planning authority South Staffordshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date21 Jul 2025 (granted, reference 24/01092/FULM, planning authority South Staffordshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorElgin Energy EsCoDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity100 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.5743, -2.2056DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority South Staffordshire, reference 24/01092/FULM)
  2. Permit applied for (planning authority South Staffordshire, reference 24/01092/FULM)

How it compares

Pool Hall Farm, Lower Penn - Battery Storage is the 248th-largest of 2,174 power plants planned, permitted or under construction in England and the 426th-largest of 3,222 in the United Kingdom by capacity; its 100 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England248th of 2,174185,888 MW<0.1%
United Kingdom426th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data1,276th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 5 data centers, measured from the coordinates in the facts above. The table shows the nearest 3.

NameKindSizeStatusDistance
Hutchison 3GData center——12 km
EE Data CentreData center——13 km
Evoque Data Center SolutionsData center——36 km

Operator and place

More from Elgin Energy EsCo

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page