Power plant · Forest of Dean, England, United Kingdom
Moat Farm - Solar Farm
Moat Farm - Solar Farm is a permitted power plant in Forest of Dean, England, United Kingdom, with 49.9 MW of capacity, operated by Elgin Energy EsCo.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Forest of Dean (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Moat Farm Newent, GL18 1JG | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (planning permission granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 19 May 2026 (permit P2061/21/FUL, Town and Country Planning Act, issued by Forest of Dean) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 25 Jan 2022 (reference P2061/21/FUL, planning authority Forest of Dean) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 19 May 2026 (granted, reference P2061/21/FUL, planning authority Forest of Dean) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Elgin Energy EsCo | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 49.9 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 82 ha (solar site area) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 51.9188, -2.3863 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Permit granted (planning authority Forest of Dean, reference P2061/21/FUL)
- Permit applied for (planning authority Forest of Dean, reference P2061/21/FUL)
How it compares
Moat Farm - Solar Farm is the 514th-largest of 2,174 power plants planned, permitted or under construction in England and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 514th of 2,174 | 185,888 MW | <0.1% |
| United Kingdom | 886th of 3,222 | 300,461 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 1,966th of 6,455 | 664,040 MW | <0.1% |
Nearby
Within 50 km of this power plant: 26 grid connections (15 operating, 322 MW), 15 substations, 3 data centers and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| DXC Technology | Data center | — | — | 8.6 km |
| Shipton Oliffe Primary | Substation | — | — | 31 km |
| Tetbury Primary | Substation | — | — | 35 km |
| Ionos data center, England | Data center | — | — | 36 km |
| Whiteway Primary | Substation | — | — | 36 km |
| Bathurst Estates grid connection | Grid connection | 49.9 MW | Operating | 36 km |
| Cirencester Solar Park grid connection | Grid connection | 25 MW | Planned | 36 km |
| Marsh Farm B PV grid connection | Grid connection | 11.4 MW | Operating | 38 km |
| nLighten Bristol | Data center | — | — | 44 km |
Operator and place
More from Elgin Energy EsCo
- Pashley Farm, Ninfield Road - Battery Energy Storage System130 MW · planned
- Pool Hall Farm, Lower Penn - Battery Storage100 MW · permitted
- Pelham Road, Upton Magna - Battery Energy Storage System100 MW · planned
- Lime Lane, Pelsall - Battery Energy Storage System100 MW
- Catsfield Christmas Tree Farm, The Stream - Battery Energy Storage System99.9 MW · planned
- Highfields Farm, Clifton Lane - Solar Panels61.9 MW · under construction
- Woodlands Farm - Solar Array49.9 MW · permitted
- Murrells End Farm - Solar Arrays49.9 MW
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.