Power plant · Newark and Sherwood, England, United Kingdom

One Earth Solar Farm

One Earth Solar Farm is a permitted solar power plant in Newark and Sherwood, England, United Kingdom, with 740 MW of capacity, operated by One Earth Solar Farm, Orsted UK Limited and PS Renewables.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNewark and Sherwood (coordinates), England (East Midlands)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
LocationBassetlaw (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
LocationEnglandNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
AddressLand surrounding the River Trent, north of South Clifton, east of Skegby, west of Thorney.Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
AddressHigh Marnham, The border of Nottinghamshire, Newark, NG23 6SFDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (post-decision, granted)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date8 Jul 2026 (permit EN010159, Planning Act 2008 development consent, issued by Secretary of State)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date8 Jul 2026 (permit EN010159, Planning Act 2008 development consent, issued by The Planning Inspectorate - National Infrastructure)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date27 Feb 2025 (reference EN010159, planning authority The Planning Inspectorate)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Application date27 Feb 2025 (reference EN010159, planning authority The Planning Inspectorate - National Infrastructure)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date8 Jul 2026 (granted, reference EN010159, planning authority The Planning Inspectorate)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date8 Jul 2026 (granted, reference EN010159, planning authority The Planning Inspectorate - National Infrastructure)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorOne Earth Solar Farm (applicant)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorOrsted UK Limited (Orsted UK Limited / PS Renewables, applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorPS Renewables (Orsted UK Limited / PS Renewables, applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity740 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsPlanning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBatteryPlanning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Area1,404 ha (application boundary)planning.data.gov.uk · record · Open Government Licence v3.0 · checked 25 Oct 2026
Area1,409 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.2303, -0.7613Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices, registers and owners' press releases, newest first. All recent changes.

  1. Permit granted (by Secretary of State for Energy Security and Net Zero, dated by the press release) · source
  2. Permit granted (planning authority The Planning Inspectorate, reference EN010159) · source
  3. Permit granted (planning authority The Planning Inspectorate - National Infrastructure, reference EN010159)
  4. Permit applied for (to Planning Inspectorate, dated by the press release) · source
  5. Permit applied for (planning authority The Planning Inspectorate, reference EN010159) · source
  6. Permit applied for (planning authority The Planning Inspectorate - National Infrastructure, reference EN010159)

Also recorded as

3 sources record One Earth Solar Farm; this page joins their facts, each with its own source. Links to any of the records lead here. How records are matched.

Name in the sourceIdentifierSourceMatched on
One Earth Solar Farmasset:pins-nsip:en010159Planning Inspectorate: National Infrastructure Projects—
One Earth Solar Farmasset:repd:14806DESNZ Renewable Energy Planning Database (REPD)Same name, technology and capacity
One Earth Solar Farmasset:neso-tec:pro-001599NESO TEC RegisterSame name, technology and company

How it compares

One Earth Solar Farm is the 56th-largest of 1,650 power plants planned, permitted or under construction in England and the 85th-largest of 2,548 in the United Kingdom by capacity; its 740 MW is 0.27% of the 278,868 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England56th of 1,650171,064 MW0.43%
United Kingdom85th of 2,548278,868 MW0.27%
All power plants planned, permitted or under construction in our data172nd of 5,799656,876 MW0.11%

Nearby

Within 50 km of this power plant: 144 grid connections (70 operating, 969 MW), 102 substations, 4 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Hall Water Treatment Works grid connectionGrid connection1.6 MWOperating3.0 km
Newton on Trent Water Works grid connectionGrid connection3.1 MWOperating4.5 km
StowSubstation——11 km
Stow Park Road grid connectionGrid connection1.19 MWOperating11 km
Digital Space DC - NewarkData center——17 km
Lea RoadSubstation——18 km
Corringham RoadSubstation——19 km
North Humber to High MarnhamTransmission line—Planned26 km
ThalesData center——38 km

Operators and place

Grid connections attached to this power plant

More from One Earth Solar Farm

Other power plants in England

All 5872 power plants in England, United Kingdom

Data on this page