Power plant · Cumberland, England, United Kingdom
Low Harker Farm, Low Harker - Battery Storage Facility
Low Harker Farm, Low Harker - Battery Storage Facility is a permitted power plant in Cumberland, England, United Kingdom, with 400 MW of capacity, operated by Zenobe Energy.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Cumberland (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Low Harker Farm, Low Harker, Harker, Carlisle, CA6 4DP | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (planning permission granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 18 Jul 2024 (permit 24/0093, Town and Country Planning Act, issued by Cumberland) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 12 Feb 2024 (reference 24/0093, planning authority Cumberland) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 18 Jul 2024 (granted, reference 24/0093, planning authority Cumberland) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Zenobe Energy | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 400 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Battery (stand-alone storage) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 54.9468, -2.9541 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchHow it compares
Low Harker Farm, Low Harker - Battery Storage Facility is the 103rd-largest of 2,174 power plants planned, permitted or under construction in England and the 157th-largest of 3,222 in the United Kingdom by capacity; its 400 MW is 0.13% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 103rd of 2,174 | 186,088 MW | 0.21% |
| United Kingdom | 157th of 3,222 | 300,661 MW | 0.13% |
| All power plants planned, permitted or under construction in our data | 351st of 6,455 | 664,240 MW | <0.1% |
Nearby
Within 50 km of this power plant: 79 grid connections (38 operating, 446 MW), 37 substations and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Harker / Hutton GSP | Substation | — | — | 0.7 km |
| Newtown of Rockcliffe grid connection | Grid connection | 99.9 MW | Planned | 0.9 km |
| Project Willow Bank grid connection | Grid connection | 99.4 MW | Planned | 0.9 km |
| Newtown Farm grid connection | Grid connection | 100 MW | Planned | 0.9 km |
| Carlisle North BSP | Substation | — | — | 1.4 km |
| Westlinton | Substation | — | — | 2.9 km |
| Cross Border Connection (England) | Transmission line | — | Planned | 24 km |
Operator and place
More from Zenobe Energy
- Eccles Battery Energy Storage System400 MW · under construction
- Kilmarnock South Substation - Battery storage300 MW
- Blackhillock Electricity Substation - Battery Energy Storage System300 MW · under construction
- Carlisle Road - Battery Energy Storage System200 MW · permitted
- Printworks Road - Stalybridge Battery Storage150 MW · permitted
- National Grid Electricity Substation, Capenhurst Lane - Battery Storage100 MW
- Shetland Battery Energy Storage System70 MW · under construction
- Wishaw Battery Storage Facility50 MW
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.