Power plant · Spelthorne, England, United Kingdom

Long Lane, Stanwell - Battery Energy Storage

Long Lane, Stanwell - Battery Energy Storage is a permitted power plant in Spelthorne, England, United Kingdom, with 49.9 MW of capacity, operated by Harwood Project One Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSpelthorne (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressE/O Long Lane, Stanwell, Staines, TW19 7AJDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date18 Jul 2025 (permit 24/01541/FUL, Town and Country Planning Act, issued by Spelthorne)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date23 Dec 2024 (reference 24/01541/FUL, planning authority Spelthorne)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date18 Jul 2025 (granted, reference 24/01541/FUL, planning authority Spelthorne)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorHarwood Project One LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.4509, -0.4630DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

Long Lane, Stanwell - Battery Energy Storage is the 514th-largest of 2,174 power plants planned, permitted or under construction in England and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England514th of 2,174186,088 MW<0.1%
United Kingdom886th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,966th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 187 substations, 157 data centers (1 operating, 88 MW), 112 grid connections (62 operating, 674 MW) and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
50MW BESS grid connectionGrid connection50 MWPlanned0.4 km
TR for Approval and Costing grid connectionGrid connection50 MWPlanned0.6 km
Serverfarm LON1 – London Data CenterData center——0.8 km
Stanwell PrimarySubstation——1.2 km
East Bedfont BSPSubstation——1.5 km
Staines BSPSubstation——1.5 km
Ready - 50MW Battery grid connectionGrid connection50 MWPlanned2.5 km
Digital Realty LHR17Data center——3.4 km
BA Boadicea House Data CentreData center——3.6 km

Operator and place

Other power plants in England

All 5809 power plants in England, United Kingdom