Grid connection · England, United Kingdom

TR for Approval and Costing grid connection

TR for Approval and Costing grid connection is a planned grid connection in England, United Kingdom, with 50 MW of capacity, held by Utility Connection Solutions Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceTR FOR APPROVAL AND COSTING grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Laleham)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderUtility Connection Solutions LimitedSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toLaleham GSP (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity50 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date29 Oct 2021SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Dec 2037 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage132 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.4555, -0.4591SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

TR for Approval and Costing grid connection is the 582nd-largest of 2,533 grid connections in England and the 885th-largest of 3,903 in the United Kingdom by capacity; its 50 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England582nd of 2,533319,370 MW<0.1%
United Kingdom885th of 3,903446,745 MW<0.1%
All grid connections in our data4,250th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 330 power plants (113 operating, 865 MW), 185 substations, 157 data centers (1 operating, 88 MW) and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Heathrow Airport Biomass CHPPower plant1.8 MWOperating0.5 km
Long Lane, Stanwell - Battery Energy StoragePower plant49.9 MWPermitted0.6 km
Serverfarm LON1 – London Data CenterData center——1.0 km
East Bedfont BSPSubstation——1.3 km
Staines BSPSubstation——1.3 km
Stanwell PrimarySubstation——1.7 km
Digital Realty LHR17Data center——2.9 km
BA Boadicea House Data CentreData center——3.0 km
Land south of Holloway LanePower plant5 MWCancelled4.0 km

Holder, grid operator and place

Other grid connections in England

All 3831 grid connections in England, United Kingdom