Grid connection · England, United Kingdom

Ready - 50MW Battery grid connection

Ready - 50MW Battery grid connection is a planned grid connection in England, United Kingdom, with 50 MW of capacity, held by Reliagen Electric Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceREADY - 50MW BATTERY grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Staines)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderReliagen Electric LtdSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toStaines BSP (via a bulk supply point)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity50 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date31 May 2022SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Dec 2037 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.4388, -0.4929SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Ready - 50MW Battery grid connection is the 538th-largest of 2,533 grid connections in England and the 804th-largest of 3,903 in the United Kingdom by capacity; its 50 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England538th of 2,533319,370 MW<0.1%
United Kingdom804th of 3,903446,745 MW<0.1%
All grid connections in our data4,076th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 305 power plants (106 operating, 849 MW), 190 substations, 155 data centers (1 operating, 88 MW) and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
East Bedfont PrimarySubstation——0.3 km
Sidney Road PrimarySubstation——0.9 km
Stanwell PrimarySubstation——1.3 km
Long Lane, Stanwell - Battery Energy StoragePower plant49.9 MWPermitted2.5 km
Serverfarm LON1 – London Data CenterData center——2.8 km
Norlands Lane Landfill Site (Extension)Power plant4 MWOperating3.2 km
Norlands Lane Landfill SitePower plant2.7 MWOperating3.4 km
British Telecom Computer CentreData center——5.2 km
Digital Realty LHR17Data center——5.3 km

Holder, grid operator and place

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page