Power plant · New Forest, England, United Kingdom

Limolands Farm Solar Array

Limolands Farm Solar Array is a cancelled power plant in New Forest, England, United Kingdom, with 5 MW of capacity, operated by Locogen.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNew Forest (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLimolands Farm, Vaggs Lane, Hordle, Lymington, SO41 0FPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (appeal refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date3 Oct 2014 (reference 14/00817, planning authority New Forest)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date30 Mar 2016 (appeal refused, reference 14/00817, planning authority New Forest)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date17 Dec 2014 (refused, reference 14/00817, planning authority New Forest)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorLocogenDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area13.6 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.7696, -1.6168DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (appeal refused, planning authority New Forest, reference 14/00817)
  2. Permit refused (planning authority New Forest, reference 14/00817)
  3. Permit applied for (planning authority New Forest, reference 14/00817)

How it compares

Limolands Farm Solar Array is the 1,758th-largest of 3,430 power plants in England and the 2,742nd-largest of 5,050 in the United Kingdom by capacity; its 5 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,758th of 3,43071,965 MW<0.1%
United Kingdom2,742nd of 5,050115,622 MW<0.1%
All power plants in our data8,380th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 192 grid connections (111 operating, 1,082 MW), 168 substations, 8 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Arnewood BSPSubstation——1.2 km
Milford-On-Sea PrimarySubstation——3.6 km
Hincheslea PrimarySubstation——3.8 km
Onyx Waste grid connectionGrid connection1.45 MWOperating5.1 km
12.35MW Walkford Road Solar grid connectionGrid connection12.5 MWPlanned5.3 km
Solar 1.425 MW grid connection at New MiltonGrid connection1.43 MWOperating5.4 km
Data Vault - Bournemouth BCP01Data center——19 km
Sky ChilworthData center——25 km
SCCData center——28 km

Operator and place

More from Locogen

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page