Power plant · Central Bedfordshire, England, United Kingdom

Greenfield Road - Samphill Solar Farm

Greenfield Road - Samphill Solar Farm is a cancelled power plant in Central Bedfordshire, England, United Kingdom, with 38.4 MW of capacity, operated by Anesco.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationCentral Bedfordshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressSamphill Solar Farm, Greenfield Road, Westoning, MK45 4SPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date23 Jun 2025 (reference CB/25/02017/FULL, planning authority Central Bedfordshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date20 Feb 2026 (refused, reference CB/25/02017/FULL, planning authority Central Bedfordshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorAnesco (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity38.4 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area62.8 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.9712, -0.4690DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (planning authority Central Bedfordshire, reference CB/25/02017/FULL)
  2. Permit applied for (planning authority Central Bedfordshire, reference CB/25/02017/FULL)

How it compares

Greenfield Road - Samphill Solar Farm is the 501st-largest of 3,953 power plants in England and the 838th-largest of 5,723 in the United Kingdom by capacity; its 38.4 MW is <0.1% of the 136,106 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England501st of 3,95385,679 MW<0.1%
United Kingdom838th of 5,723136,106 MW<0.1%
All power plants in our data2,603rd of 12,7051,210,931 MW<0.1%

Nearby

Within 50 km of this power plant: 35 substations, 29 data centers (1 operating, 88 MW), 24 grid connections (11 operating, 114 MW) and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Data center, Dunstable (OSM way 526426719)Data center——8.5 km
Starwood HouseData center——18 km
Pulsant Milton Keynes SE-1Data center——22 km
East Claydon GSPSubstation——31 km
Cokes Lane PrimarySubstation——34 km
Amersham GSPSubstation——36 km
Generation 99 MW grid connection at Amersham MainGrid connection99 MWPlanned37 km
Pembridge Farm grid connectionGrid connection131 MWPlanned41 km
Bicester 49.9MW - PV grid connectionGrid connection44 MWPlanned42 km

Operator and place

More from Anesco

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page