Power plant · Epping Forest, England, United Kingdom

East End Solar Farm

East End Solar Farm is a permitted power plant in Epping Forest, England, United Kingdom, with 49.9 MW of capacity, operated by Low Carbon Solar Park 18.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEpping Forest (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressAdj Harlow Road, Roydon, Harlow, CM19 5HHDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (appeal granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date3 May 2024 (permit EPF/1974/22, Town and Country Planning Act, issued by Epping Forest)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date26 Aug 2022 (reference EPF/1974/22, planning authority Epping Forest)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date3 May 2024 (granted, reference EPF/1974/22, planning authority Epping Forest)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date3 May 2024 (appeal granted, reference EPF/1974/22, planning authority Epping Forest)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date28 Jun 2023 (refused, reference EPF/1974/22, planning authority Epping Forest)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorLow Carbon Solar Park 18DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area69.9 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.7707, 0.0456DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (appeal granted, planning authority Epping Forest, reference EPF/1974/22)
  2. Permit granted (planning authority Epping Forest, reference EPF/1974/22)
  3. Permit refused (planning authority Epping Forest, reference EPF/1974/22)
  4. Permit applied for (planning authority Epping Forest, reference EPF/1974/22)

How it compares

East End Solar Farm is the 514th-largest of 2,174 power plants planned, permitted or under construction in England and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England514th of 2,174185,888 MW<0.1%
United Kingdom886th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data1,966th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 96 data centers (1 operating, 88 MW), 51 substations, 19 grid connections (10 operating, 98.6 MW), 1 AI supercomputer and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Kao Data KLON-01Data center——5.8 km
Kao Data KLON-02Data center——5.8 km
NVIDIA Cambridge-1AI supercomputer202 H100eOperating5.9 km
Google Datacentre Waltham CrossData center——11 km
North London (Electricity Line) ReinforcementTransmission line—Permitted20 km
Tertiary Study grid connectionGrid connection57 MWPlanned29 km
Solar 6.935 MW grid connection at Maiden NewtonGrid connection6.94 MWOperating31 km
Willesden GSPSubstation——34 km
Canal Bank 11kV PrimarySubstation——34 km

Operator and place

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page