Power plant · Runnymede, England, United Kingdom

Chertsey Water Treatment Works

Chertsey Water Treatment Works is a power plant in Runnymede, England, United Kingdom, with 1.3 MW of capacity, operated by Affinity Water Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationRunnymede (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressChertsey Water Treatment Works, Lyne Lane, Chertsey, KT16 0ARDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2022DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorAffinity Water LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1.3 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.3955, -0.5400DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned

How it compares

Chertsey Water Treatment Works is the 3,166th-largest of 3,430 power plants in England and the 4,704th-largest of 5,050 in the United Kingdom by capacity; its 1.3 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England3,166th of 3,43071,965 MW<0.1%
United Kingdom4,704th of 5,050115,622 MW<0.1%
All power plants in our data11,398th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 196 substations, 151 data centers (1 operating, 88 MW), 125 grid connections (69 operating, 737 MW) and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Waste 3.325 MW grid connection at CausewayGrid connection3.33 MWOperating2.5 km
MVEE PrimarySubstation——3.8 km
Ark Data Centres - Longcross ParkData center——4.1 km
Egham PrimarySubstation——4.2 km
Causeway PrimarySubstation——4.5 km
Ready - 50MW Battery grid connectionGrid connection50 MWPlanned5.8 km
Redcentric ByfleetData center——6.8 km
Ready - 200MW Battery grid connectionGrid connection200 MWPlanned6.9 km
Serverfarm LON1 – London Data CenterData center——8.2 km

Operator and place

More from Affinity Water Limited

Other power plants in England

All 5809 power plants in England, United Kingdom