Power plant · Breckland, England, United Kingdom

Burntstalk Solar Park

Burntstalk Solar Park is a power plant in Breckland, England, United Kingdom, with 11.5 MW of capacity, operated by Lightsource Renewable Energy.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationBreckland (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLow Road, Narford, Kings Lynn, NorfolkDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2013DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date21 Dec 2012 (permit 3PL/2012/1036/F, Town and Country Planning Act, issued by Breckland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date8 Oct 2012 (reference 3PL/2012/1036/F, planning authority Breckland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date21 Dec 2012 (granted, reference 3PL/2012/1036/F, planning authority Breckland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorLightsource Renewable EnergyDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity11.5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area25 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.6738, 0.6306DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Breckland, reference 3PL/2012/1036/F)
  3. Permit applied for (planning authority Breckland, reference 3PL/2012/1036/F)

How it compares

Burntstalk Solar Park is the 1,011th-largest of 3,430 power plants in England and the 1,730th-largest of 5,050 in the United Kingdom by capacity; its 11.5 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,011th of 3,43071,965 MW<0.1%
United Kingdom1,730th of 5,050115,622 MW<0.1%
All power plants in our data6,536th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 3 data centers and 2 transmission lines, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
Longmarsh Green EnergyData center—Planned17 km
Kings Lynn B Connection ProjectTransmission line—Permitted18 km
US Air Force data center, BrandonData center——31 km
Positive ParkData center——40 km
Norwich to TilburyTransmission line—Planned45 km

Operator and place

More from Lightsource Renewable Energy

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page