Broken Scar Water Treatment Works Solar Farm is a permitted power plant in North Yorkshire, England, United Kingdom, with 9 MW of capacity, operated by Northumbrian Water Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNorth Yorkshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressS/O Broken Scar Water Treatment Works Cleasby, DL2DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date13 Jun 2022 (permit 22/00041/FULL, Town and Country Planning Act, issued by North Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date21 Jan 2022 (ref. 22/00041/FULL, North Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date13 Jun 2022 (granted, ref. 22/00041/FULL, North Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorNorthumbrian Water LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area11.9 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates54.5194, -1.6040DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Broken Scar Water Treatment Works Solar Farm is the 1,513th-largest of 2,174 power plants planned, permitted or under construction in England and the 2,343rd-largest of 3,222 in the United Kingdom by capacity; its 9 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,513th of 2,174186,088 MW<0.1%
United Kingdom2,343rd of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data5,437th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 242 grid connections (122 operating, 1,283 MW) and 124 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Broken Scar Treatment Works grid connectionGrid connection3.4 MWOperating0.5 km
Broken Scar Treatment Works grid connectionGrid connection3.1 MWOperating0.5 km
Darlington WestSubstation——1.5 km
Gas 2.5 MW grid connection at Darlington WestGrid connection2.5 MWOperating3.0 km
Darlington 132/6kV DirectSubstation——3.8 km
Darlington 33/11kVSubstation——3.8 km

Operator and place