Power plant · County Durham, England, United Kingdom
Benridge Farm, Fillpoke Lane - Battery Energy Storage System
Benridge Farm, Fillpoke Lane - Battery Energy Storage System is a planned battery storage plant in County Durham, England, United Kingdom, with 12 MW of capacity, operated by Development at Benridge Farm.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | County Durham (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | The East South And W/O Benridge Farm, Fillpoke Lane, Blackhall Rocks, Hartlepool, TS27 4BT | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Planned (planning application submitted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 18 Jul 2025 (reference DM/25/01964/FPA, planning authority County Durham) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Development at Benridge Farm (applicant) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 12 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Battery (co-located with re) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 54.7342, -1.2732 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Permit applied for (planning authority County Durham, reference DM/25/01964/FPA)
How it compares
Benridge Farm, Fillpoke Lane - Battery Energy Storage System is the 1,134th-largest of 1,650 power plants planned, permitted or under construction in England and the 1,822nd-largest of 2,548 in the United Kingdom by capacity; its 12 MW is <0.1% of the 279,068 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,134th of 1,650 | 171,264 MW | <0.1% |
| United Kingdom | 1,822nd of 2,548 | 279,068 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 4,598th of 5,799 | 657,076 MW | <0.1% |
Nearby
Within 50 km of this power plant: 274 grid connections (137 operating, 1,359 MW), 164 substations and 5 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Benridge Solar grid connection | Grid connection | 60 MW | Planned | 1.9 km |
| Hulam Farm grid connection | Grid connection | 50 MW | Planned | 3.1 km |
| Hartmoor | Substation | — | — | 3.7 km |
| Hartmoor 66/20kV | Substation | — | — | 3.7 km |
| Solar 42 MW grid connection at Sheraton Solar | Grid connection | 42 MW | Planned | 3.9 km |
| Amberton Road | Substation | — | — | 5.6 km |
| DXC Wynyard Data Center | Data center | — | — | 11 km |
| Lumen Technologies data center, Middlesbrough | Data center | — | — | 17 km |
| Pulsant data center, England | Data center | — | — | 21 km |
Operator and place
More from Development at Benridge Farm
- Benridge Farm, Fillpoke Lane - Solar Panels48 MW · planned
Other power plants in England
- Drax Power Station Biomass Units2,580 MW
- Ratcliffe-on-Soar2,021 MW
- Cottam2,000 MW
- Walpole Flexible Generation Project2,000 MW
- West Burton2,000 MW
- Eggborough1,960 MW
- Staythorpe1,828 MW
- Fiddler’s Ferry1,510 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- Wikidata. Wikidata, CC0 1.0.