Banks Renewables is linked to 30 assets and rights in the United Kingdom: it operates 29 power plants and holds a grid connection. It is a subsidiary of Brookfield Asset Management Ltd. It has one subsidiary in the data, linked to 1 asset or right.
Portfolio
The 30 assets and rights Banks Renewables owns, operates or holds, by class, with its role in each, across its 5 records. Sizes are the whole asset's, so they are not added up: the sources give no share for this owner.
Power plants 29
| Power plant | Location | Role | Capacity |
|---|---|---|---|
| Pond Industrial Park, Whitburn Road - Pond Battery Storage | West Lothian, Scotland, United Kingdom | Applicant | 200 MW |
| Lethans Wind Farm | East Ayrshire, Scotland, United Kingdom | Applicant | 106 MW |
| Kype Muir Wind Farm | South Lanarkshire, Scotland, United Kingdom | Operator | 88.4 MW |
| Kype Muir Wind Farm Extension | South Lanarkshire, Scotland, United Kingdom | Operator | 67.2 MW |
| Lethans Wind Farm Extension | East Ayrshire, Scotland, United Kingdom | Applicant | 66 MW |
| Birneyknowe Wind Farm | Scottish Borders, Scotland, United Kingdom | Applicant | 60 MW |
| Middle Muir Wind Farm | South Lanarkshire, Scotland, United Kingdom | Operator | 51 MW |
| Barnsdale Road Solar Park | Leeds, England, United Kingdom | Operator | 40 MW |
| Barnsdale Road Solar Park - Battery Energy Storage | Leeds, England, United Kingdom | Applicant | 40 MW |
| Mill Rig Wind Farm | South Lanarkshire, Scotland, United Kingdom | Operator | 36 MW |
| High Cumnock Wind Farm | East Ayrshire, Scotland, United Kingdom | Applicant | 27.2 MW |
| Bandirran Wind Farm | Perth and Kinross, Scotland, United Kingdom | Applicant | 20.4 MW |
| Penny Hill Lane | Rotherham, England, United Kingdom | Operator | 19.8 MW |
| Bank Field Wind Farm | Redcar and Cleveland, England, United Kingdom | Applicant | 17 MW |
| Crofthill Wind Farm | South Lanarkshire, Scotland, United Kingdom | Applicant | 17 MW |
| Knockendurrick Wind Farm | Dumfries and Galloway, Scotland, United Kingdom | Applicant | 14 MW |
| Windy Bank Windfarm | County Durham, England, United Kingdom | Applicant | 14 MW |
| Armistead Wind Farm | Westmorland and Furness, England, United Kingdom | Operator | 12 MW |
| Moor House Wind Farm | Darlington, England, United Kingdom | Operator | 12 MW |
| Weddicar Rigg Wind Farm | Cumberland, England, United Kingdom | Applicant | 12 MW |
| Hook Moor | Leeds, England, United Kingdom | Operator | 10.3 MW |
| Killington Wind Farm | Westmorland and Furness, England, United Kingdom | Applicant | 10.2 MW |
| Lambs Hill | Stockton-on-Tees, England, United Kingdom | Operator | 8 MW |
| Marr Windfarm | Doncaster, England, United Kingdom | Operator | 8 MW |
| Heysham South Wind Farm | Lancaster, England, United Kingdom | Operator | 7.5 MW |
| Hazlehead | Barnsley, England, United Kingdom | Operator | 6 MW |
| Land At Penny Hill Lane | Rotherham, England, United Kingdom | Applicant | 5 MW |
| Pond Green Energy Park | West Lothian, Scotland, United Kingdom | Applicant | 5 MW |
| Hazlehead Wind Farm Battery | Barnsley, England, United Kingdom | Applicant | 1 MW |
Grid connections 1
| Grid connection | Location | Role | Capacity |
|---|---|---|---|
| Tealing Energy Park grid connection | Scotland, United Kingdom | Holder | 1,400 MW |
By country
Where the assets and rights are.
- The United Kingdom30 in 2 classes
Latest events
Dated events about Banks Renewables and its assets from official notices and registers, newest first: the latest 8 of 79. All recent changes.
- Construction started: Barnsdale Road Solar Park
- Permit granted: Pond Industrial Park, Whitburn Road - Pond Battery Storage (planning authority Scottish Government (S36), reference ECU00004765)
- Construction started: Mill Rig Wind Farm
- Commissioned: Kype Muir Wind Farm Extension
- Withdrawn: Barnsdale Road Solar Park - Battery Energy Storage (planning authority Leeds, reference 23/03233/FU)
- Permit granted: Lethans Wind Farm Extension (planning authority Scottish Government (S36), reference ECU00002221)
- Permit applied for: Pond Industrial Park, Whitburn Road - Pond Battery Storage (planning authority Scottish Government (S36), reference ECU00004765)
- Permit granted: Mill Rig Wind Farm (planning authority South Lanarkshire, reference P/21/1127)
Group
Parent companies
From Banks Renewables up to its ultimate parent in the data.
- Banks Renewables
- Brookfield Asset Management Ltd.
Subsidiaries
1 company under Banks Renewables, direct and through other subsidiaries.
| Subsidiary | Held through | Share | Assets and rights |
|---|---|---|---|
| Glen Water Wind Farm Limited | Direct | — | 1 |
Subsidiaries' portfolio
1 asset or right across the subsidiaries, each counted once. This total is apart from the portfolio above; together, the group links to 31.
- Power plant1
Partners and counterparties
Owners, operators and grid operators on the same assets.
Facts
| Fact | Value | Source |
|---|---|---|
| Location | England | Companies House bulk company data · record · OGL v3 · checked 24 Oct 2026 |
| Location | United Kingdom | GLEIF LEI · record · CC0 1.0 · checked 24 Oct 2026 |
| LEI | 213800K5261ULWF4R876 | Rare Context entity resolution · record · CC0 1.0 · checked 24 Oct 2026 GLEIF LEI · record · CC0 1.0 · checked 24 Oct 2026 |
| Company number | 02387216 | Companies House bulk company data · record · OGL v3 · checked 24 Oct 2026 GLEIF LEI · record · CC0 1.0 · checked 24 Oct 2026 |
| Register status | Active | Companies House bulk company data · record · OGL v3 · checked 24 Oct 2026 |
| Company type | Private Limited Company | Companies House bulk company data · record · OGL v3 · checked 24 Oct 2026 |
| Incorporated | 22 May 1989 | Companies House bulk company data · record · OGL v3 · checked 24 Oct 2026 |
| Industry (SIC) | 35110 - Production of electricity | Companies House bulk company data · record · OGL v3 · checked 24 Oct 2026 |
Also recorded as
Sources name Banks Renewables under 5 records; this page joins them. Links to any of them lead here.
| Name in the source | Identifier | Source |
|---|---|---|
| ONPATH ENERGY LIMITED | party:company-number:gb-02387216 | Companies House bulk company data |
| BANKS RENEWABLES LIMITED | party:lei:213800K5261ULWF4R876 | GLEIF LEI |
| Banks Renewables | party:name:banks-renewables | DESNZ Renewable Energy Planning Database (REPD) |
| OnPath Energy | party:name:onpath-energy | DESNZ Renewable Energy Planning Database (REPD) |
| OnPath Energy Limited | party:name:onpath-energy-limited | DESNZ Renewable Energy Planning Database (REPD) |
Research on Banks Renewables.Its full portfolio, its parent companies, and an introduction to the people who decide on buying and selling.
Request researchData on this page
- Contains public sector information licensed under the Open Government Licence v3.0. Companies House bulk company data, OGL v3.
- Companies House PSC snapshot. Companies House PSC snapshot, Free, unsupported daily snapshot.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- GLEIF LEI. GLEIF LEI, CC0 1.0.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.