Armistead Wind Farm is a power plant in Westmorland and Furness, England, United Kingdom, with 12 MW of capacity, operated by Banks Renewables.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Westmorland and Furness (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Land to the east of Crosslands Farm, near Old Hutton, Kendal South Lakeland, LA6 2QJ | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 2013 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Onshore or offshore | Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 15 Jul 2010 (permit SL/2008/0318, Town and Country Planning Act, issued by Westmorland and Furness) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 25 Mar 2008 (reference SL/2008/0318, planning authority Westmorland and Furness) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 10 Nov 2008 (refused, reference SL/2008/0318, planning authority Westmorland and Furness) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 15 Jul 2010 (appeal granted, reference SL/2008/0318, planning authority Westmorland and Furness) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 15 Jul 2010 (granted, reference SL/2008/0318, planning authority Westmorland and Furness) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Banks Renewables | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 12 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Units | 6 units (2 MW per unit) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Wind Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 54.2771, -2.6360 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchHow it compares
Armistead Wind Farm is the 931st-largest of 3,430 power plants in England and the 1,630th-largest of 5,050 in the United Kingdom by capacity; its 12 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 931st of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 1,630th of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 6,154th of 12,008 | 1,173,302 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Permit issued (Town and Country Planning Act), no. SL/2008/0318
- Started operating
Nearby
Within 50 km of this power plant: 112 grid connections (57 operating, 365 MW), 65 substations, 1 transmission line and 1 gas storage facility, measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Armistead Wind Farm grid connection | Grid connection | 17.1 MW | Operating | 1.2 km |
| Old Hutton BESS grid connection | Grid connection | 99.9 MW | Planned | 3.4 km |
| Greaves Farm grid connection | Grid connection | 4 MW | Operating | 3.6 km |
| Kirkby Lonsdale | Substation | — | — | 8.2 km |
| Sedbergh | Substation | — | — | 8.2 km |
| Kendal | Substation | — | — | 8.2 km |
| East Irish Sea Transmission Project | Transmission line | — | Planned | 45 km |
| Preesall Saltfield Underground Gas Storage | Gas storage facility | — | Cancelled | 47 km |
Operator and place
Grid connections attached to this power plant
More from Banks Renewables
- Pond Industrial Park, Whitburn Road - Pond Battery Storage200 MW · permitted
- Kype Muir Wind Farm88.4 MW
- Kype Muir Wind Farm Extension67.2 MW
- Lethans Wind Farm Extension66 MW · permitted
- Birneyknowe Wind Farm60 MW
- Middle Muir Wind Farm51 MW
- Mill Rig Wind Farm36 MW · under construction
- High Cumnock Wind Farm27.2 MW
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.