Grid connection · Scotland, United Kingdom

Torness grid connection

Torness grid connection is a grid connection in Scotland, United Kingdom, with 1,250 MW of capacity, held by EDF Energy Nuclear Generation Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationScotland (connects at Torness 400/132kV)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
StatusOperating (built)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
HolderEDF Energy Nuclear Generation LimitedNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Attached toTornessNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Capacity1,250 MWNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyNuclearNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorSP Transmission plcNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Torness grid connection is the 21st-largest of 1,192 grid connections in Scotland and the 80th-largest of 3,903 in the United Kingdom by capacity; its 1,250 MW is 0.28% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland21st of 1,19288,894 MW1.4%
United Kingdom80th of 3,903446,745 MW0.28%
All grid connections in our data146th of 7,9281,372,494 MW<0.1%

Holder, grid operator and place