Grid connection · Scotland, United Kingdom

South Clyde Energy Centre grid connection

South Clyde Energy Centre grid connection is a planned grid connection in Scotland, United Kingdom, with 45 MW of capacity, held by Fortum Glasgow Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationScotland (connects at Braehead Park)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
HolderFortum Glasgow LimitedSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity45 MWSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyLandfill gasSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSP Distribution plcSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date10 Jul 2020SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date13 Aug 2026 (target energisation)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

South Clyde Energy Centre grid connection is the 325th-largest of 1,192 grid connections in Scotland and the 1,071st-largest of 3,903 in the United Kingdom by capacity; its 45 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland325th of 1,19288,894 MW<0.1%
United Kingdom1,071st of 3,903446,745 MW<0.1%
All grid connections in our data4,466th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Was due to connect; the register does not list it as connected

Holder, grid operator and place

More from Fortum Glasgow Limited

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom