Grid connection · Scotland, United Kingdom
Loch Turret WTW-EXP grid connection
Loch Turret WTW-EXP grid connection is a grid connection in Scotland, United Kingdom, with 1.9 MW of capacity, held by Scottish Water.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | LOCH TURRET WTW-EXP grid connection | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | Scotland (connection site: CRIEFF) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Operating (CONNECTED) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Holder | Scottish Water | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Crieff Primary (via: primary) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 1.9 MW | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Hydro | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Scottish Hydro Electric Power Distribution plc | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 11 kV | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
Know more about this grid connection, or want an introduction to its holder? Ask us.
How it compares
Loch Turret WTW-EXP grid connection is the 1,061st-largest of 1,192 grid connections in Scotland and the 3,427th-largest of 3,903 in the United Kingdom by capacity; its 1.9 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| Scotland | 1,061st of 1,192 | 88,894 MW | <0.1% |
| United Kingdom | 3,427th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 7,123rd of 7,616 | 1,281,251 MW | <0.1% |
Holder, grid operator and place
More from Scottish Water
- Deerdykes WWTW grid connection2 MW
- Invercannie Waterworks PV grid connection1.88 MW
- Nigg Sea Outfall grid connection1.62 MW
- Glenhove Pumping Station, Glenhove Road - BESS3.1 MW · planned
- Glenhove Pumping Station, Glenhove Road - Solar Array1.9 MW · planned
- Meadowhead Sewage Treatment Plant, Meadowhead Road - Solar Array1.56 MW · permitted
- St Johns Terrace - Solar PV Array1.3 MW · permitted
- Blairlinnans Water Treatment Plant, Stirling Road - Solar PV Panels1.28 MW
Other grid connections in Scotland
- Marram Wind Offshore Wind Farm grid connection3,000 MW
- OWPL Windfarm grid connection2,250 MW
- Caledonia Offshore Wind Farm grid connection2,000 MW
- Machair Offshore Wind Farm grid connection2,000 MW
- Arven Offshore Wind Farm grid connection1,800 MW
- Bellrock Offshore Wind Farm grid connection1,800 MW
- Earba PSH grid connection1,800 MW
- Glen Earrach PSH grid connection1,800 MW
Data on this page
- CAISO queue report. CAISO queue report, CAISO Privacy and Terms of Use.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, No restriction on the posted data.
- PJM New Services Queue. PJM New Services Queue, No restriction on the posted data.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.