Grid connection · Scotland, United Kingdom

Greentoft Farm grid connection

Greentoft Farm grid connection is a planned grid connection in Scotland, United Kingdom, with 30 MW of capacity, held by Neven Point Wind Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceGREENTOFT FARM grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Thurso)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderNeven Point Wind LtdSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity30 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyWindSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date17 Aug 2022SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 May 2030 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates59.1620, -2.7674SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Greentoft Farm grid connection is the 423rd-largest of 1,192 grid connections in Scotland and the 1,333rd-largest of 3,903 in the United Kingdom by capacity; its 30 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland423rd of 1,19288,894 MW<0.1%
United Kingdom1,333rd of 3,903446,745 MW<0.1%
All grid connections in our data4,846th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 45 power plants (16 operating, 45.2 MW) and 15 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Eday Tidal PrimarySubstation——2.0 km
Eday PrimarySubstation——2.6 km
Magallanes (FoW - EMEC)Power plant2 MWOperating3.0 km
SR-2000 (FoW - EMEC)Power plant2 MWOperating3.0 km
The Fall of Warness Tidal Scheme, (FoW - EMEC)Power plant2 MWPermitted3.0 km
Sanday PrimarySubstation——7.0 km

Holder, grid operator and place