Grid connection · Scotland, United Kingdom

Fetteresso Wind - 37MW grid connection

Fetteresso Wind - 37MW grid connection is a planned grid connection in Scotland, United Kingdom, with 37 MW of capacity, held by Natural Power Consultants.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceFETTERESSO WIND - 37MW grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Fettersso Grid)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderNatural Power ConsultantsSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity37 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyWindSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date26 Jan 2016SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Sept 2026 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Fetteresso Wind - 37MW grid connection is the 371st-largest of 1,192 grid connections in Scotland and the 1,220th-largest of 3,903 in the United Kingdom by capacity; its 37 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland371st of 1,19288,894 MW<0.1%
United Kingdom1,220th of 3,903446,745 MW<0.1%
All grid connections in our data4,690th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Was due to connect; the register does not list it as connected

Holder, grid operator and place

More from Natural Power Consultants

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom

Data on this page