Grid connection · Scotland, United Kingdom

Dunmill Energy Storage Scheme grid connection

Dunmill Energy Storage Scheme grid connection is a planned grid connection in Scotland, United Kingdom, with 76.2 MW of capacity, held by Renewable Energy Systems.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceDUNMILL ENERGY STORAGE SCHEME grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connection site: BRIDGE OF DUN GRID)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (ACCEPTED TO CONNECT)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderRenewable Energy SystemsSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toBridge of Dun Primary (via: primary)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity76.2 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date5 Apr 2023SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Jun 2032 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates56.7204, -2.5564SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Dunmill Energy Storage Scheme grid connection is the 90th-largest of 1,192 grid connections in Scotland and the 563rd-largest of 3,903 in the United Kingdom by capacity; its 76.2 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland90th of 1,19288,894 MW<0.1%
United Kingdom563rd of 3,903446,745 MW<0.1%
All grid connections in our data3,337th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 159 power plants (38 operating, 1,580 MW) and 63 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Bridge of Dun GSPSubstation——0.0 km
Bridge of Dun PrimarySubstation——0.0 km
Balwyllo Farm, Dun - Energy Storage FacilityPower plant50 MWPermitted0.2 km
Dunmill, Substation Dun - Battery Energy StoragePower plant49.9 MWPermitted0.3 km
Arrats Mill, Arrat - Solar Photovoltaic ArrayPower plant18.5 MWPermitted1.6 km
Brechin PrimarySubstation——5.1 km

Holder, grid operator and place

More from Renewable Energy Systems

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom

Data on this page