Grid connection · England, United Kingdom

Town Lane BESS grid connection

Town Lane BESS grid connection is a planned grid connection in England, United Kingdom, with 30 MW of capacity, held by Leading Initiatives Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceTOWN LANE BESS grid connectionSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Penwortham West GSP / Stanah GSP Group)SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
HolderLeading Initiatives LtdSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity30 MWSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorElectricity North West LimitedSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date14 May 2021SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage132 kVSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates53.6170, -2.6908SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Town Lane BESS grid connection is the 857th-largest of 2,533 grid connections in England and the 1,333rd-largest of 3,903 in the United Kingdom by capacity; its 30 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England857th of 2,533319,370 MW<0.1%
United Kingdom1,333rd of 3,903446,745 MW<0.1%
All grid connections in our data4,564th of 7,6161,281,251 MW<0.1%

Nearby

Within 50 km of this grid connection: 404 power plants (124 operating, 1,620 MW), 17 data centers, 5 substations, 3 gas storage facilities and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Charnock Richard - Battery StoragePower plant30 MWOperating0.4 km
Vause Farm - Battery StoragePower plant20 MWPermitted0.4 km
Thompson House Equestrian farmPower plant5 MWOperating2.2 km
Data center, England (OSM way 1551100328)Data center——16 km
Verizon WarringtonData center——23 km
Iron MountainData center——23 km
Morgan and Morecambe Offshore Wind Farms Transmission AssetsTransmission line—Permitted29 km
East Irish Sea Transmission ProjectTransmission line—Planned30 km
Preesall Saltfield Underground Gas StorageGas storage facility—Cancelled37 km

Holder, grid operator and place

Other grid connections in England

All 3831 grid connections in England, United Kingdom