Grid connection · England, United Kingdom
Thornton Road grid connection
Thornton Road grid connection is a planned grid connection in England, United Kingdom, with 48.1 MW of capacity, held by Pathfinder Clean Energy (PACE) Ukdev Ltd.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England (connects at Sellindge 132kV) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Status | Planned (accepted to connect) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Holder | Pathfinder Clean Energy (PACE) Ukdev Ltd | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Capacity | 48.1 MW | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Technology | Battery storage | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Technology | Solar | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Grid operator | South Eastern Power Networks plc (UK Power Networks, South East England licence area) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Queue date | 24 Jul 2023 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Connection date | 31 Oct 2036 (target energisation) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Voltage | 132 kV | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Coordinates | 51.2092, 1.2578 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
How it compares
Thornton Road grid connection is the 835th-largest of 3,539 grid connections in England and the 1,182nd-largest of 4,870 in the United Kingdom by capacity; its 48.1 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 835th of 3,539 | 341,715 MW | <0.1% |
| United Kingdom | 1,182nd of 4,870 | 467,981 MW | <0.1% |
| All grid connections in our data | 4,387th of 8,618 | 1,355,288 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Entered the connection queue
- Due to connect
Nearby
Within 50 km of this grid connection: 137 power plants (51 operating, 4,420 MW), 62 substations, 3 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Tilmanstone Colliery | Power plant | 10 MW | Operating | 1.5 km |
| Snowdown Colliery | Power plant | 5 MW | Cancelled | 2.5 km |
| Elvington Battery Energy Storage | Power plant | 49.5 MW | Planned | 2.6 km |
| Lightweight Aggregates 11kV | Substation | — | — | 2.7 km |
| Wingham 11kV | Substation | — | — | 5.6 km |
| Betteshanger Grid 33kV | Substation | — | — | 6.3 km |
| The Bunker - South East Data Centre | Data center | — | — | 7.4 km |
| Richborough Connection Project | Transmission line | — | Permitted | 11 km |
| Sota Datacentre | Data center | — | — | 39 km |
Holder, grid operator and place
- Pathfinder Clean Energy (PACE) Ukdev LtdHolder
- South Eastern Power Networks plcGrid operator
- Grid connections in England, United Kingdom4,837
- Grid connections in the United Kingdom6,880
- Battery storage grid connections in the UK1,141
- Solar grid connections in the UK1,755
- The United Kingdom: country profile
- Largest grid connections
More from Pathfinder Clean Energy (PACE) Ukdev Ltd
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.
- UK Power Networks. UK Power Networks open data portal, CC BY 4.0.