Grid connection · England, United Kingdom

Sandy Brow Lane (Spencers Farm) grid connection

Sandy Brow Lane (Spencers Farm) grid connection is a planned grid connection in England, United Kingdom, with 82.8 MW of capacity, held by Balance Power Projects Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connection site: Kirkby)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (Accepted to Connect)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
HolderBalance Power Projects LimitedSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity82.8 MWSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSP ManwebSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Oct 2024 (target energisation)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage132 kVSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Sandy Brow Lane (Spencers Farm) grid connection is the 406th-largest of 2,533 grid connections in England and the 533rd-largest of 3,903 in the United Kingdom by capacity; its 82.8 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England406th of 2,533319,370 MW<0.1%
United Kingdom533rd of 3,903446,745 MW<0.1%
All grid connections in our data3,223rd of 7,6161,281,251 MW<0.1%