Power plant · Perth and Kinross, Scotland, United Kingdom

Hallyburton - Battery Storage

Hallyburton - Battery Storage is a permitted power plant in Perth and Kinross, Scotland, United Kingdom, with 100 MW of capacity, operated by Balance Power Projects Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationPerth and Kinross (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressHallyburton, Kettins, Blairgowrie, PH13 9LRDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date2 Oct 2025 (permit ECU00004931, Electricity Act 1989 section 36, issued by Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date6 Dec 2024 (reference ECU00004931, planning authority Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date2 Oct 2025 (granted, reference ECU00004931, planning authority Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorBalance Power Projects LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity100 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates56.5400, -3.2373DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Hallyburton - Battery Storage is the 146th-largest of 872 power plants planned, permitted or under construction in Scotland and the 426th-largest of 3,222 in the United Kingdom by capacity; its 100 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland146th of 87299,272 MW0.1%
United Kingdom426th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,276th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 96 grid connections (27 operating, 394 MW) and 70 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
49.9MW BESS grid connectionGrid connection49.9 MWPlanned0.3 km
Hallyburton BESS grid connectionGrid connection49.9 MWPlanned0.3 km
Abroath BESS (MSID 8771) EXP grid connectionGrid connection33.3 MWOperating1.9 km
Coupar Angus GSPSubstation——2.2 km
Coupar Angus PrimarySubstation——2.2 km
Blairgowrie PrimarySubstation——7.4 km

Operator and place

More from Balance Power Projects Limited

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page