RARE CONTEXT Request research

Grid connection · England, United Kingdom

Redhill Landfill Site 3 grid connection

Redhill Landfill Site 3 grid connection is a grid connection in England, United Kingdom, with 3.2 MW of capacity, connected by South Eastern Power Networks plc (UK Power Networks, South East England licence area).

Map: where Redhill Landfill Site 3 grid connection lies
51.2452, -0.1433 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Nutfield 11kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusOperating (connected)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Attached toRedhill 2 (matched by shared name+coordinates+technology+capacity, 1.06 km away)Rare Context entity resolution · CC0 1.0 · checked 25 Oct 2026
Attached toNutfield 11kV (via a primary substation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity3.2 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologyLandfill gasUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorSouth Eastern Power Networks plc (UK Power Networks, South East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date12 Nov 2006UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage11 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.2452, -0.1433UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Latest events

Dated events about this grid connection and the records linked to it from official notices, registers and owners' press releases, newest first. All recent changes.

  1. Commissioned: Redhill 2
  2. Permit granted: Redhill 2 (planning authority Tandridge)
  3. Permit applied for: Redhill 2 (planning authority Tandridge)

How it compares

Redhill Landfill Site 3 grid connection is the 2,720th-largest of 3,539 grid connections in England and the 3,749th-largest of 4,870 in the United Kingdom by capacity; its 3.2 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England2,720th of 3,539341,715 MW<0.1%
United Kingdom3,749th of 4,870467,981 MW<0.1%
All grid connections in our data7,470th of 8,6181,355,288 MW<0.1%

Nearby

Within 50 km of this grid connection: 545 substations, 305 power plants (123 operating, 3,055 MW), 140 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Patteson Court Landfill SitePower plant1.8 MWOperating0.2 km
Copyhold Works IncineratorPower plant20 MWCancelled1.0 km
Unit 3Data center——1.0 km
Redhill 2Power plant3 MWOperating1.1 km
Unit 2Data center——1.1 km
Unit 1Data center——1.2 km
Redhill Primary 11kVSubstation——1.2 km
Nutfield 11kVSubstation——1.2 km
Reigate 11kVSubstation——3.0 km

Grid operator and place

More from South Eastern Power Networks plc

Other grid connections in England

All 4837 grid connections in England, United Kingdom