RARE CONTEXT Request research

Grid connection · England, United Kingdom

Red Tile Windfarm - 1 grid connection

Red Tile Windfarm - 1 grid connection is a grid connection in England, United Kingdom, with 10 MW of capacity, held by Fenland Windfarms Ltd.

Map: where Red Tile Windfarm - 1 grid connection lies
52.4301, -0.0179 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Peterborough Central 33kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusOperating (connected)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderFenland Windfarms LtdUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity10 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologyWindUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date8 Dec 2006UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates52.4301, -0.0179UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

Red Tile Windfarm - 1 grid connection is the 1,805th-largest of 3,539 grid connections in England and the 2,551st-largest of 4,870 in the United Kingdom by capacity; its 10 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,805th of 3,539341,715 MW<0.1%
United Kingdom2,551st of 4,870467,981 MW<0.1%
All grid connections in our data6,152nd of 8,6181,355,288 MW<0.1%

Nearby

Within 50 km of this grid connection: 392 power plants (152 operating, 5,159 MW), 102 substations, 7 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Red TilePower plant24 MWOperating0.6 km
Old Brick Works (Station Road, Warboys)Power plant1.5 MWCancelled3.7 km
Alan Bartlett & Sons SolarPower plant1.2 MWOperating4.7 km
Chatteris Primary 11kVSubstation——4.8 km
Bury Grid 11kVSubstation——7.8 km
Bury Primary 11kVSubstation——7.8 km
Positive ParkData center——18 km
Data center, England (OSM way 87850427)Data center——22 km
Redcentric CambridgeData center——25 km

Holder, grid operator and place

More from Fenland Windfarms Ltd

Other grid connections in England

All 4837 grid connections in England, United Kingdom