Grid connection · England, United Kingdom
Reaps Moss Wind Farm grid connection
Reaps Moss Wind Farm grid connection is a grid connection in England, United Kingdom, with 10.7 MW of capacity, held by Reaps Moss Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | REAPS MOSS WIND FARM grid connection | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Rossendale) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Operating (connected) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Holder | Reaps Moss Limited | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Reaps Moss Wind Farm (matched by name+coordinates+technology+capacity, 0.29 km away) | Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026 |
| Attached to | Rossendale BSP (via a bulk supply point) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 10.7 MW | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Wind | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Electricity North West Limited | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Connection date | 1 Aug 2015 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 33 kV | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 53.7017, -2.1599 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchLatest events
Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.
- Commissioned: Reaps Moss Wind Farm
- Permit granted: Reaps Moss Wind Farm (planning authority Rossendale, reference 2007/125)
- Permit applied for: Reaps Moss Wind Farm (planning authority Rossendale, reference 2007/125)
How it compares
Reaps Moss Wind Farm grid connection is the 1,321st-largest of 2,533 grid connections in England and the 2,088th-largest of 3,903 in the United Kingdom by capacity; its 10.7 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,321st of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 2,088th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 5,947th of 7,928 | 1,372,494 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 525 substations, 340 power plants (101 operating, 722 MW), 19 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Todmorden Moor | Power plant | 12.3 MW | Operating | 0.3 km |
| Reaps Moss Wind Farm | Power plant | 10.2 MW | Operating | 0.3 km |
| Gorpley Wind Farm | Power plant | 9.2 MW | Cancelled | 0.4 km |
| Wesley Place Bacup | Substation | — | — | 2.9 km |
| Whitworth | Substation | — | — | 3.6 km |
| Todmorden | Substation | — | — | 3.8 km |
| Lloyds Banking Group Copley | Data center | — | — | 18 km |
| Data center, England (OSM way 403124345) | Data center | — | — | 18 km |
| Redcentric Elland Data Centre | Data center | — | — | 22 km |
Holder, grid operator and place
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.