Grid connection · England, United Kingdom

Kentishes (Lyons Hall) grid connection

Kentishes (Lyons Hall) grid connection is a grid connection in England, United Kingdom, with 10.8 MW of capacity, held by Energy and System Technical Limited.

Map: where Kentishes (Lyons Hall) grid connection lies
51.9082, 0.5926 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Braintree Local 33kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusOperating (connected)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderEnergy and System Technical LimitedUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity10.8 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date1 May 2018UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.9082, 0.5926UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

Kentishes (Lyons Hall) grid connection is the 1,786th-largest of 3,539 grid connections in England and the 2,526th-largest of 4,870 in the United Kingdom by capacity; its 10.8 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,786th of 3,539341,715 MW<0.1%
United Kingdom2,526th of 4,870467,981 MW<0.1%
All grid connections in our data6,123rd of 8,6181,355,288 MW<0.1%

Nearby

Within 50 km of this grid connection: 309 power plants (124 operating, 3,549 MW), 201 substations, 7 data centers, 1 transmission line and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Kentishes Solar FarmPower plant5 MWOperating0.9 km
Kentish Farm 2 - Battery Energy StoragePower plant22.5 MWPlanned1.1 km
Kentish Farm 2 - Solar FarmPower plant16.5 MWPlanned1.1 km
Lake & Elliot Primary 11kVSubstation——4.2 km
Halstead Primary 11kVSubstation——4.9 km
Braintree Depot Primary 11kVSubstation——5.0 km
Bramford to TwinsteadTransmission line—Permitted21 km
NVIDIA Cambridge-1AI supercomputer202 H100eOperating35 km
Kao Data KLON-02Data center——35 km

Holder, grid operator and place

More from Energy and System Technical Limited

Other grid connections in England

All 4837 grid connections in England, United Kingdom