Kentish Farm 2 grid connection

Kentish Farm 2 grid connection is a planned grid connection in England, United Kingdom, with 3.2 MW of capacity, held by Kentish Solar Farm 3 Limited.

Map: where Kentish Farm 2 grid connection lies
51.9051, 0.6046 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Braintree Local 33kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusPlanned (accepted to connect)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderKentish Solar Farm 3 LimitedUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity3.2 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Queue date29 Sept 2017UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date6 Jan 2025 (target energisation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.9051, 0.6046UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

Kentish Farm 2 grid connection is the 2,720th-largest of 3,539 grid connections in England and the 3,749th-largest of 4,870 in the United Kingdom by capacity; its 3.2 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England2,720th of 3,539341,715 MW<0.1%
United Kingdom3,749th of 4,870467,981 MW<0.1%
All grid connections in our data7,470th of 8,6181,355,288 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Was due to connect; the register does not list it as connected

Nearby

Within 50 km of this grid connection: 305 power plants (124 operating, 3,543 MW), 197 substations, 7 data centers, 1 transmission line and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Kentishes Solar FarmPower plant5 MWOperating0.2 km
Kentish Farm 2 - Battery Energy StoragePower plant22.5 MWPlanned0.2 km
Kentish Farm 2 - Solar FarmPower plant16.5 MWPlanned0.2 km
Lake & Elliot Primary 11kVSubstation——4.4 km
Halstead Primary 11kVSubstation——4.8 km
Braintree Depot Primary 11kVSubstation——4.9 km
Bramford to TwinsteadTransmission line—Permitted21 km
NVIDIA Cambridge-1AI supercomputer202 H100eOperating36 km
Kao Data KLON-02Data center——36 km

Holder, grid operator and place

Other grid connections in England