Grid connection · England, United Kingdom

Igas Energy plc grid connection

Igas Energy plc grid connection is a planned grid connection in England, United Kingdom, with 2 MW of capacity, held by Star Energy Group plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceIGAS ENERGY PLC grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Midhurst)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderStar Energy Group plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toMidhurst Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity2 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date5 Aug 2022SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Sept 2027 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage11 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates50.9331, -0.7564SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Igas Energy plc grid connection is the 2,165th-largest of 2,533 grid connections in England and the 3,341st-largest of 3,903 in the United Kingdom by capacity; its 2 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England2,165th of 2,533319,370 MW<0.1%
United Kingdom3,341st of 3,903446,745 MW<0.1%
All grid connections in our data7,347th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 234 power plants (91 operating, 703 MW), 156 substations, 19 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Midhurst PrimarySubstation——4.0 km
Hunters Race Solar ParkPower plant9.3 MWOperating8.2 km
Strettington Solar FarmPower plant5 MWOperating8.7 km
Broadley CopsePower plant2.2 MWOperating9.1 km
Chichester PrimarySubstation——9.4 km
Chichester BSPSubstation——9.5 km
SSE data center, HavantData center——17 km
Aquind InterconnectorTransmission line—Planned20 km
IBM HorshamData center——30 km