Grid connection · England, United Kingdom

Hornsea Power Station 4 grid connection

Hornsea Power Station 4 grid connection is a planned grid connection in England, United Kingdom, with 2,600 MW of capacity, held by Orsted Hornsea Project Four Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connection site: Creyke Beck 400kV Substation)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (Scoping)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
HolderOrsted Hornsea Project Four LimitedNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Attached toHornsea Power Station 4NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Capacity2,600 MWNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyWind OffshoreNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNational Grid Electricity Transmission plcNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Connection date31 Oct 2029 (stage 2, cumulative 2,600 MW)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Connection date30 Oct 2028 (stage 1, cumulative 1,500 MW)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Hornsea Power Station 4 grid connection is the 11th-largest of 2,678 grid connections in England and the 12th-largest of 4,493 in the United Kingdom by capacity; its 2,600 MW is 0.57% of the 459,551 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England11th of 2,678322,469 MW0.81%
United Kingdom12th of 4,493459,551 MW0.57%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Stage 1 due to connect, 1,500 MW in total
  2. Stage 2 due to connect, 2,600 MW in total

Holder, grid operator and place

Other grid connections in England

All 3977 grid connections in England, United Kingdom

Data on this page