RARE CONTEXT Request research

Grid connection · England, United Kingdom

Gyron Maylands Datacentre grid connection

Gyron Maylands Datacentre grid connection is a grid connection in England, United Kingdom, with 8 MW of capacity, held by NTT Global Data Centers EMEA UK Ltd.

Map: where Gyron Maylands Datacentre grid connection lies
51.7645, -0.4435 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Industrial Primary 11kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusOperating (connected)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderNTT Global Data Centers EMEA UK Ltd.UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Attached toIndustrial Primary 11kV (via a primary substation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity8 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologyOilUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date29 Oct 2018UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage11 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.7645, -0.4435UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

Gyron Maylands Datacentre grid connection is the 1,974th-largest of 3,539 grid connections in England and the 2,783rd-largest of 4,870 in the United Kingdom by capacity; its 8 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,974th of 3,539341,715 MW<0.1%
United Kingdom2,783rd of 4,870467,981 MW<0.1%
All grid connections in our data6,446th of 8,6181,355,288 MW<0.1%

Nearby

Within 50 km of this grid connection: 504 substations, 398 power plants (147 operating, 2,885 MW), 141 data centers (1 operating, 88 MW), 1 transmission line and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
NTT Hemel Hempstead 2Data center——0.1 km
Industrial Primary 11kVSubstation——0.5 km
NTT Hemel Hempstead 3Data center——0.6 km
Hemel North Primary 11kVSubstation——0.6 km
G Park Maxted Road - Solar PanelsPower plant1.25 MWCancelled0.8 km
NTT Hemel Hempstead 4Data center——1.3 km
Amazon Boundary WayPower plant2 MWCancelled1.3 km
St Pauls Primary 11kVSubstation——1.7 km
Flamsteadbury FarmPower plant4.5 MWCancelled3.7 km

Holder, grid operator and place

More from NTT Global Data Centers EMEA UK Ltd.

Other grid connections in England

All 4837 grid connections in England, United Kingdom

Data on this page