Grid connection · England, United Kingdom
Ellen Road BESS grid connection
Ellen Road BESS grid connection is a planned grid connection in England, United Kingdom, with 15 MW of capacity, held by Ylem Energy Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | ELLEN ROAD BESS grid connection | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Rochdale) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Holder | Ylem Energy Limited | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Rochdale GSP (via a bulk supply point) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 15 MW | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Battery storage | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Electricity North West Limited | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 20 Dec 2023 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 33 kV | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 53.6005, -2.1056 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchHow it compares
Ellen Road BESS grid connection is the 1,191st-largest of 2,533 grid connections in England and the 1,889th-largest of 3,903 in the United Kingdom by capacity; its 15 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,191st of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 1,889th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 5,700th of 7,928 | 1,372,494 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 561 substations, 359 power plants (102 operating, 793 MW), 23 data centers and 2 gas storage facilities, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Ellenroad Farm, Bentgate Street - Battery Energy Storage System | Power plant | 30 MW | Permitted | 0.0 km |
| Kingsway | Substation | — | — | 1.3 km |
| Milnrow | Substation | — | — | 1.7 km |
| Shaw | Substation | — | — | 2.4 km |
| Miall Power - Energy Storage Facility | Power plant | 5 MW | Cancelled | 3.1 km |
| Mossdown Road | Power plant | 10 MW | Cancelled | 4.5 km |
| Data center, England (OSM way 703959498) | Data center | — | — | 15 km |
| Asanti Manchester | Data center | — | — | 16 km |
| Evolution @ Agecroft Commerce Park | Data center | — | — | 17 km |
Holder, grid operator and place
More from Ylem Energy Limited
- Knuzden BESS 60MW grid connection30 MW
- Medlock BESS 30MW grid connection20 MW
- Northacre Industrial Park grid connection7.22 MW
- Ladybank Landfill Lower Melville Wood grid connection2.4 MW
- Lochhead Landfill grid connection2.3 MW
- Clayton Hall Quarry grid connection1.43 MW
- Brookhill Landfill grid connection1 MW
- Cooksland Farm, Old Snydale -Battery Energy Storage50 MW · permitted
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.