Dengie Farm grid connection

Dengie Farm grid connection is a grid connection in England, United Kingdom, with 13.8 MW of capacity, held by Dengie Solar Park Limited.

Map: where Dengie Farm grid connection lies
51.6767, 0.8596 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Maldon Grid 33kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusOperating (connected)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderDengie Solar Park LimitedUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Attached toDengie - Solar PV array (matched by name+coordinates+technology, 1.26 km away)Rare Context entity resolution · CC0 1.0 · checked 25 Oct 2026
Capacity13.8 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologyBattery storageUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date24 Sept 2025UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.6767, 0.8596UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Latest events

Dated events about this grid connection and the records linked to it from official notices, registers and owners' press releases, newest first. All recent changes.

  1. Permit granted: Dengie - Solar PV array (planning authority Maldon, reference 23/01236/FULM)
  2. Permit applied for: Dengie - Solar PV array (planning authority Maldon, reference 23/01236/FULM)

How it compares

Dengie Farm grid connection is the 1,668th-largest of 3,539 grid connections in England and the 2,371st-largest of 4,870 in the United Kingdom by capacity; its 13.8 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,668th of 3,539341,715 MW<0.1%
United Kingdom2,371st of 4,870467,981 MW<0.1%
All grid connections in our data5,944th of 8,6181,355,288 MW<0.1%

Nearby

Within 50 km of this grid connection: 303 power plants (128 operating, 7,710 MW), 194 substations, 8 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Dengie - Solar PV arrayPower plant19 MWPermitted1.3 km
Dengie - Solar PV arrayPower plant5 MWPermitted1.3 km
Tillingham Primary 11kVSubstation——1.6 km
Turncole Wind FarmPower plant17.5 MWOperating2.9 km
Bradwell Primary 11kVSubstation——5.3 km
Burnham Primary 11kVSubstation——6.2 km
CityFibre CabinetsData center——19 km
Imperium 315Data center——28 km
Bramford to TwinsteadTransmission line—Permitted37 km

Holder, grid operator and place

Other grid connections in England

All 4837 grid connections in England, United Kingdom

Data on this page