Grid connection · England, United Kingdom

Brilliant Harvest 004 Ltd - Battery (Add CAP) grid connection

Brilliant Harvest 004 Ltd - Battery (Add CAP) grid connection is a planned grid connection in England, United Kingdom, with 7 MW of capacity, held by Evans Energy Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceBRILLIANT HARVEST 004 LTD - BATTERY (ADD CAP) grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connection site: NORRINGTON)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (ACCEPTED TO CONNECT)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderEvans Energy LtdSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toNorrington BSP (via: bsp)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity7 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date6 Apr 2018SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date9 Apr 2026 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.1743, -2.0346SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Brilliant Harvest 004 Ltd - Battery (Add CAP) grid connection is the 1,577th-largest of 2,678 grid connections in England and the 2,704th-largest of 4,493 in the United Kingdom by capacity; its 7 MW is <0.1% of the 459,551 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,577th of 2,678322,469 MW<0.1%
United Kingdom2,704th of 4,493459,551 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Connected

Nearby

Within 50 km of this grid connection: 140 substations, measured from the coordinates in the facts above. The table shows the nearest 3.

NameKindSizeStatusDistance
Codford PrimarySubstation——2.1 km
Crockerton PrimarySubstation——10 km
Stapleford PrimarySubstation——10 km

Holder, grid operator and place

More from Evans Energy Ltd

Other grid connections in England

All 3977 grid connections in England, United Kingdom

Data on this page