Grid connection · England, United Kingdom

Bretton grid connection

Bretton grid connection is a planned grid connection in England, United Kingdom, with 35 MW of capacity, held by Corin Hughes Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Chester Main GT4 / Crane Bank GT1 / Guilden Sutton GT1 / Saltney G2A)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
HolderCorin Hughes LtdSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity35 MWSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSP Manweb plcSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date12 May 2022SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Oct 2037 (target energisation)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage132 kVSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Bretton grid connection is the 809th-largest of 2,533 grid connections in England and the 1,254th-largest of 3,903 in the United Kingdom by capacity; its 35 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England809th of 2,533319,370 MW<0.1%
United Kingdom1,254th of 3,903446,745 MW<0.1%
All grid connections in our data4,454th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Holder, grid operator and place

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page