Grid connection · England, United Kingdom

(ANM) Land At Sewardstone Road grid connection

(ANM) Land At Sewardstone Road grid connection is a planned grid connection in England, United Kingdom, with 99.9 MW of capacity, connected by Eastern Power Networks plc (UK Power Networks, East England licence area).

Map: where (ANM) Land At Sewardstone Road grid connection lies
51.6712, 0.0120 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Brimsdown (EPN))UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusPlanned (accepted to connect)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity99.9 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologyBattery storageUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Queue date21 Jun 2023UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date31 Oct 2033 (target energisation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage132 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.6712, 0.0120UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

(ANM) Land At Sewardstone Road grid connection is the 355th-largest of 3,539 grid connections in England and the 458th-largest of 4,870 in the United Kingdom by capacity; its 99.9 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England355th of 3,539341,715 MW<0.1%
United Kingdom458th of 4,870467,981 MW<0.1%
All grid connections in our data3,209th of 8,6181,355,288 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 572 substations, 434 power plants (160 operating, 5,738 MW), 132 data centers (1 operating, 88 MW), 1 transmission line and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Waltham Point Distribution CentrePower plant1.8 MWOperating1.5 km
Waltham Abbey Primary 11kVSubstation——1.6 km
Iceland, Solar Way - Solar Photovoltaic ArrayPower plant2.64 MWPermitted2.2 km
West Essex Golf Club, Bury Road - Solar FarmPower plant10.7 MWCancelled2.3 km
Brimsdown North Grid 33kVSubstation——2.7 km
Brimsdown South Grid 11kVSubstation——2.7 km
Google Waltham CrossData center88 MWOperating5.0 km
Google Datacentre Waltham CrossData center——5.0 km
Virtus LONDON1Data center——5.1 km

Grid operator and place

More from Eastern Power Networks plc

Other grid connections in England

All 4837 grid connections in England, United Kingdom