(ANM) Feeringbury Farm grid connection

(ANM) Feeringbury Farm grid connection is a planned grid connection in England, United Kingdom, with 15 MW of capacity, held by Padero Solaer Limited.

Map: where (ANM) Feeringbury Farm grid connection lies
51.8627, 0.7160 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Braintree Local 33kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusPlanned (accepted to connect)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderPadero Solaer LimitedUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity15 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Queue date10 Jul 2022UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date31 Oct 2032 (target energisation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.8627, 0.7160UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

(ANM) Feeringbury Farm grid connection is the 1,574th-largest of 3,539 grid connections in England and the 2,247th-largest of 4,870 in the United Kingdom by capacity; its 15 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,574th of 3,539341,715 MW<0.1%
United Kingdom2,247th of 4,870467,981 MW<0.1%
All grid connections in our data5,806th of 8,6181,355,288 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 267 power plants (108 operating, 6,811 MW), 166 substations, 4 data centers, 1 transmission line and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Skye Green Solar FarmPower plant15 MWPermitted0.5 km
Coggeshall Primary 11kVSubstation——2.2 km
Marks Tey Primary 11kVSubstation——4.1 km
Highfields Farm (Braintree)Power plant2.8 MWOperating4.2 km
Highfields Farm (Colchester)Power plant12.2 MWOperating4.2 km
Tiptree Primary 11kVSubstation——5.5 km
Bramford to TwinsteadTransmission line—Permitted19 km
CityFibre CabinetsData center——33 km
Imperium 315Data center——35 km

Holder, grid operator and place

More from Padero Solaer Limited

Other grid connections in England

All 4837 grid connections in England, United Kingdom

Data on this page