(ANM) Admiralty Road grid connection

(ANM) Admiralty Road grid connection is a planned grid connection in England, United Kingdom, with 49.9 MW of capacity, held by BAT-NR30 Limited.

Map: where (ANM) Admiralty Road grid connection lies
52.5856, 1.7349 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Norwich)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusPlanned (accepted to connect)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderBAT-NR30 LimitedUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Attached toAdmiralty Road - Battery Energy Storage Facility (matched by name+coordinates+technology+capacity, 0.1 km away)Rare Context entity resolution · CC0 1.0 · checked 25 Oct 2026
Capacity49.9 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologyBattery storageUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Queue date28 Dec 2021UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date31 Oct 2032 (target energisation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage132 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates52.5856, 1.7349UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Latest events

Dated events about this grid connection and the records linked to it from official notices, registers and owners' press releases, newest first. All recent changes.

  1. Permit granted: Admiralty Road - Battery Energy Storage Facility (planning authority Great Yarmouth, reference 06/24/0123/F)
  2. Permit applied for: Admiralty Road - Battery Energy Storage Facility (planning authority Great Yarmouth, reference 06/24/0123/F)

How it compares

(ANM) Admiralty Road grid connection is the 698th-largest of 3,539 grid connections in England and the 997th-largest of 4,870 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England698th of 3,539341,715 MW<0.1%
United Kingdom997th of 4,870467,981 MW<0.1%
All grid connections in our data4,183rd of 8,6181,355,288 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 152 power plants (47 operating, 2,005 MW), 66 substations and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.

NameKindSizeStatusDistance
Admiralty Road - Battery Energy Storage FacilityPower plant50 MWPermitted0.1 km
South Denes RoadPower plant6 MWCancelled0.2 km
Great YarmouthPower plant420 MWOperating0.2 km
GT Yarmouth Grid 11kVSubstation——0.3 km
GT Yarmouth Grid 33kVSubstation——0.7 km
Magdalen Way Primary 11kVSubstation——1.8 km
Norwich to TilburyTransmission line—Planned31 km
LionLink InterconnectorTransmission line—Planned45 km