Data center · England, United Kingdom

Pulsant Maidenhead

Pulsant Maidenhead is a data center in England, United Kingdom, operated by Pulsant.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandOpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026
AddressPriors Way, MaidenheadOpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026
OperatorPulsantOpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026
Building footprint1,749 m² (building, 2 buildings)OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026
Coordinates51.5003, -0.7083OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026

Research on this data center and its operator.Who owns it up to the parent company, its power supply, grid connection and planning status, and an introduction to the operator.

Request research

How its operator compares

Pulsant operates 8 of the 191 data centers in the United Kingdom in our data with a named owner; 3 owners have more. Counts cover the data centers in our data that name an owner, holder or operator; an asset with several owners counts for each.

Operator in United KingdomRankData centersShare
Equinix, Inc.1st136.8%
Digital Realty2nd105.2%
Virtus2nd105.2%
Pulsant4th84.2%
NTT Limited5th63.1%

Nearby

Within 50 km of this data center: 319 power plants (105 operating, 1,354 MW), 224 substations, 156 grid connections (78 operating, 845 MW) and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Braywick Road PrimarySubstation——2.2 km
Taplow PrimarySubstation——3.2 km
Maidenhead BSPSubstation——3.4 km
Slough Sewage Treatment WorksPower plant1.2 MWOperating5.2 km
Car Park Legoland Windsor Resort, Winkfield Road - PV solar photovoltaicPower plant1.2 MWPermitted5.4 km
Slough Multifuel Extension ProjectPower plant60 MWPermitted6.1 km
Power Station grid connectionGrid connection8 MWOperating6.2 km
Eton College PV grid connectionGrid connection3.96 MWPlanned6.2 km
Generation 59.8 MW grid connection at SloughGrid connection59.8 MWOperating6.4 km