The Limes 11kV Substation

The Limes 11kV Substation is an 11 kV primary substation in England, United Kingdom, with 7.4 MVA of demand headroom and 18.4 MVA of generation headroom, operated by Eastern Power Networks plc (UK Power Networks, East England licence area).

Map: where The Limes 11kV lies
51.5818, 0.4508 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Demand headroom7.4 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Generation headroom18.4 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Firm capacity19.1 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LevelPrimary substationUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage11 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.5818, 0.4508UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.

Nearby

Within 50 km of this substation: 374 power plants (156 operating, 8,559 MW), 366 grid connections (257 operating, 2,836 MW), 64 data centers (1 operating, 88 MW), 1 AI supercomputer and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Howard Chase grid connectionGrid connection4.56 MWOperating0.1 km
(ANM) Barleylands Road grid connectionGrid connection49.9 MWPlanned1.5 km
Whites Farm - Battery StoragePower plant49.9 MWCancelled1.6 km
Barleylands Solar FarmPower plant17 MWPermitted2.2 km
Imperium 315Data center——2.4 km
Nevendon Battery Park grid connectionGrid connection10 MWOperating2.8 km
Ford Research And Engineering Centre, Dunton - Solar FarmPower plant5.2 MWOperating2.9 km
CityFibre CabinetsData center——13 km
Fujitsu Data CentreData center——17 km

Grid operator and place

Grid connections attached to this substation

More from Eastern Power Networks plc

Other substations in England

All 2633 substations in England, United Kingdom

Data on this page