Substation · England, United Kingdom
March Grid 33kV Substation
March Grid 33kV Substation is a 33 kV primary substation in England, United Kingdom, with 7.1 MVA of demand headroom, operated by Eastern Power Networks plc (UK Power Networks, East England licence area).
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Grid operator | Eastern Power Networks plc (UK Power Networks, East England licence area) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Demand headroom | 7.1 MVA | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Firm capacity | 58.5 MVA | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Level | Primary substation | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Voltage | 33 kV | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Coordinates | 52.5496, 0.0860 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.
Nearby
Within 50 km of this substation: 333 power plants (136 operating, 4,968 MW), 178 grid connections (115 operating, 1,917 MW), 7 data centers and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Boardinghouse Wind Farm | Power plant | 10.3 MW | Operating | 2.1 km |
| March Landfill Site grid connection | Grid connection | 1.01 MW | Operating | 2.2 km |
| Fenmarc Fenland AD Plant (Waste AD) | Power plant | 1.5 MW | Operating | 2.5 km |
| Longhill Wind Turbine grid connection | Grid connection | 2 MW | Operating | 2.7 km |
| Fenmarc grid connection | Grid connection | 2.5 MW | Operating | 2.7 km |
| Long Hill Road | Power plant | 2 MW | Operating | 2.7 km |
| Positive Park | Data center | — | — | 4.3 km |
| Data center, England (OSM way 87850427) | Data center | — | — | 24 km |
| Longmarsh Green Energy | Data center | — | Planned | 26 km |
Grid operator and place
More from Eastern Power Networks plc
- Canvey Primary 11kVsubstation
- Thorley Primary 11kVsubstation
- Peterborough South Grid 11kVsubstation
- Westbury Primary 11kVsubstation
- Laxfield Primary 11kVsubstation
- Fulbourn Grid 33kVsubstation
- Earlham Grid 33kVsubstation
- Hunstanton Primary 11kVsubstation
Candidate sites around this substation
4 sites of land near March Grid 33kV have it as nearest substation. Each site page gives its area, its distance to the substation and its site score; owners are on request.
- 1.08 ha brownfield site at Davern Workwear Ltd, Elliott Road, MARCH, Fenland0.79 km · score 25
- 1.54 ha brownfield site at Site Of Former Kingswood Park Residential Home Kingswood Road March…, Fenland0.99 km · score 22
- 1.88 ha brownfield site at Former Highways Depot, Queens Street, MARCH, Fenland1.16 km · score 20
- 2.47 ha brownfield site at Land North Of 3A - 9, Bridge Lane, Wimblington, Fenland3.52 km · score 7
Other substations in England
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.